Sunday, November 8, 2015

EpDc Industrial Site

In October 2014, we were the small contractor employees surveyed a location of new candidate electrical project at Waste Processing Plant in Bogor Indonesia. The Chief engineer (Owner) of the Waste Processing Plant took us to look around the location, where the location would be used as the expansion of the electrical network were located approximately 900 m from the nearest power source ( POWER DISTRIBUTION SUBSTATION ). He started at point 1 with ended at point 4 as shown in Figure 1.1 below:


Figure plpi 1.1 Location

He needed the cable from point 1 to the point 2 to be underground cables where point 1 is the Power Distribution Substations with MCCB 400A on LVMDP. This MCCB 400A would be the main source of the whole Electrical Network Distribution plus the engineer said that Generator is added for Back up source with COS ( Change Over Switch )
Point 2 is planned to be a new panel with some MCBs FUJI brand.The Indonesian Contractors Employees are familiar with Scheneider brand but although the engineer was Indonesia native should use Fuji brand because of factory owners are Japanese. The point of no 3 at the Figure 1.1 is the existing panel that several MCCBs within panel will be modified . At last from point 3 to point 4 is the overhead electrical distribution network with a total of 10 pieces of electric poles. At the end of the Electric Pole there is a new panel that would supply a spot light on each after second Electrical Pole plus 7 pieces of 3Ø Pumps 3.7 KW each. The several of  Electrical Material are shown in Figure plpi 1.2. He wanted us to design electrical and expected to be completed no later than one week.

Figure plpi 1.2 Layout

As a contractor we will certainly work hard otherwise we would lose that job. By working mightily finally we completed our task. Previously in EPDC HOUSE and EPDC EXAMPLES INDUSTRIAL /BUSINESS there are five stages sequence that we had to do for designing of electrical construction, but in this case the stage is not applicable because the engineer couldn’t decide with certainty any electrical device that will be installed at the end point (point 4). Of course we obeyed his will by reason of job opportunities and money.

The Electrical Construction is described as follows:
Step 1: Build each panel at point no 1,2,3 and 4
Step 2: Determine cable type and size between each point
Step 3: Determine physics construction each and between point
Step 4: Combine them in layout

We will do step by step.

Step 1:
Panel A : Panel inside Power Distribution Substation at Point no 1 is named LVMDP ( Low Voltage Main Distribution Panel ) which have 2 MCCB 400A each as output. The Chief Engineer asked us to use one of the both MCCBs as main source then add COS which switch other source ( generator ) in case failure supply.
Panel B : There are two MCCB 3Ø 250A and six MCCB 3Ø. All MCCBs must be arranged starting from higher MCCB followed by the lower.
Panel C : MCCB 3Ø 150A and 100A are replaced by MCCB 3Ø 250A and 200A.
Panel D : Panel will supply 7 motors 3.7 Kilo watt and spotlight 1500Watt
  
We often see the size main MCCB panel become smaller than the sum of MCCB branch , this is not a problem because of the use of load simultaneity can only 60% or 70 %, for example in panel D : MCCB 100A has 6 sub MCCB 20A .
Panel A, B, C dan D which are to be design shown in Figure plpi 1.3


Figure plpi 1.3 Single Line Diagram

Step 2: cable type and size between each point

NO
POWER ( VA )
MCB ( Ampere )
Main Cable
1
450
2
3 x 2.5 mm²
2
900
4
3 x 2.5 mm²
3
1300
6
3 x 4 mm²
4
2200
10
3 x 4 mm²
5
3500
16
3 x 4 mm²
6
4400
20
3 x 4 mm²
7
5500
25
3 x 4 mm²
8
7700
35
3 x 6 mm²
9
11000
50
3 x 6 mm²




10
6600
3 x 10
4 x 4 mm²
11
10600
3 x 16
4 x 6 mm²
12
13200
3 x20
4 x 10 mm²
13
16500
3 x 25
4 x 10 mm²
14
23000
3 x 35
4 x 16 mm²
15
33000
3 x 50
4 x 16 mm²
16
41500
3 x 63
4 x 25 mm²
17
53000
3 x 82
4 x 35 mm²
18
66000
3 x 100
4 x 50 mm²
19
82500
3 x 125
4 x 50 mm²
20
105000
3 x 160
4 x 70 mm²
21
131000
3 x 200
4 x 95 mm²
22
171000
3 x 250
4 x 120 mm²
23
197000
3 x 300
4 x 150 mm²
24
329000
3 x 500
4 x 240 mm²
25
414000
3 x 630
4 x 300 mm²
Table 1.a 

Cable between Panel A and B.
The cable size of MCCB 400A as a source in Panel A is between row no 23 and 24 in Tabel 1.a above ( blue color ). There is no NYY 4 x 270 cable available at electrical store . The best choice is 4 x 240 mm² but the chief engineer didn’t like it with reason quite difficult to be installed, then we choose double cable of NYY 4 x 195 mm². If it double cable, the size cable of 195 become 2x195 = 390 mm². It means cable become stronger , higher rating ampere and easier to be installed. Underground NYY cable type is have to use pipe AW type, the other choice is using NYFgbY type without pipe. In this case Chief Engineer approved NYFGbY type.

Cable between Panel B and C.
The source for current distribution to Panel C is MCCB 250A on Panel B. According to Table 1.a above, the cabel is NYY 4 x 120 mm² and would be distributed via tray.

Cable between Panel C and D.
Overhead distribution using Overhead Aluminium Cable, NFA2X 3 x 70 mm² + 1x 50 mm²
Type Aluminium. MCCB vs Twisted Cable ( Aluminium) as shown in Table 1.b


NO
MCB ( Ampere )
Main Cable
1
125
35 mm²
2
125
50 mm²
3
200
70 mm²
Table 1.b

Ten spotlights Total 1500 Watt. Each spotlight has 15 Watt and each second pole has 2 spotlight as shown in Figure plpi 1.4. Actually, the Lamps can be connected to a twisted cable using Photocell Switches , but the owner prefers Timer Switch in panel D so we add cable NYY.



Figure plpi 1.4  


Spotlight Cable
We usually found cable 2.5 mm² is connected to several lamps but concerning distance 400 m between EP1 and EP10, it’s necessary to calculate drop voltage, so we get the better cable size

Drop voltage while Lamps 1500 Watt is connected as shown in figure plpi 1.4 can be found according to formulas :

electrical planning (EpDc) for Contractor, Colledge,Student
DROP VOLTAGE FORMULAS


Light or lamp is suggested drop voltage 2%, but in this case owner need higher quality voltage with drop voltage about 1.15% or (1.15%x220V) =2.5 Volt. If max drop voltage = 2.5 V, Find Cable size of Spottlight 
Refer to equation 2 in FORMULAS: q = (2L x P)/(V x ∆V x λ)
We get : ∆V = (2L x P)/(V x λx q)
And refer to Figure plpi 1.4 :

∆V9 = (2L x P)/(V x λx q) = (2L9 x P)/(220 x 56 x q)= (2.40 x 5.30)/(220.56.q) = (80 x 150)/(12320.q)=0.97/q

∆V7 = (2L x P)/(V x λx q) = (2L7 x P)/(220 x 56 x q)= (2.80 x 4.30)/(220.56.q) = (160 x 120)/(12320.q)=1.56/q

∆V5 = (2L x P)/(V x λx q) = (2L5 x P)/(220 x 56 x q)= (2.80 x 3.30)/(220.56.q) = (160 x 90)/(12320.q)=1.17/q

∆V3 = (2L x P)/(V x λx q) = (2L3 x P)/(220 x 56 x q)= (2.80 x 2.30)/(220.56.q) = (160 x 60)/(12320.q)=0.78/q

∆V1 = (2L x P)/(V x λx q) = (2L1 x P)/(220 x 56 x q)= (2.80 x 30)/(220.56.q) = (160 x 30)/(12320.q)=0.78/q=0.39/q

Then, ∆V = ∆V9 + ∆V7 + ∆V5 + ∆V3 + ∆V1  with ∆V= 2.5 Volt

2.5 = ∆V9 + ∆V7 + ∆V5 + ∆V3 + ∆V1  =  0.97/q + 1.56/q + 1.17/q + 0.78/q + 0.39/q = 4.87/q
So, q = 4.87/2.5 = 1.9 mm² ≈ 2.5 mm² or Cable NYY 2x2.5 mm² outdoor cable, if indoor type NYM.

Motor 3Ø (3.7KW) Cable
In order to find cable size of motor 1Ø or 3Ø, we need to calculate I(Ampere) of the motor first, with formulas:

Electrical Planning (EpDc) for Contractor, Colledge,Student
Table 1.b MCB For Motor


I = P/(1.73 x VLL Cos Ø)= 3700/(1.73 x 380 x 0.85)= 6.6 A

MCB = 250% X 6.6 = 16.5 A ≈ 20 A
Regarding the relay or the motor sensor is an electronic parts so it is not discussed here.

Step 3 :
Physics Construction Between Point no 1 and 2 is Underground Cable NYFGbY 2x(4 x 95) mm² with length 280 M. Every Outdoor Panel is suggested using Grounding with R≤ 5 Ω.  EP use Grounding every 200 meter or every 5 EP with R ≤ 10 Ω. Grounding on EP is made every 200 meter but in this case grounding is placed on EP1 and EP10. Grounding on Panel is similar to EPDC Industrial/Business Example 1
The Complete Construction or detail is shown in As Built Drawing in Figure plpi 1.5 include Autocad File ( 2009 Version or above) here.










Thursday, October 29, 2015

EpDc Building

A director of new small company at Kemayoran Jakarta presented me a isometric drawing as shown in Figure KBJ 1.1. He had a Civil Mechanical Electrical (CME) Building Project at EJIP Bekasi, He had designed all Civil and Mechanical by himself except the Electrical then tried me to design Electrical Construction. That was my first designing. The TL lamps on the Figure KBJ 1.1 are rectangular boxes, the box with 2x36 WATT each.
This Post shows some tricks of electrical consultant company to design electrical construction of  Public Houses, Goverment, Business , High Risk , and Industrial Building with limiting voltage 220V, 380V and 20KV, also Electrical Network Distribution Low Voltage and Medium Voltage.
( With f = 50 hz, PUIL standard is adopted from IEC, NEC Standard). Each problem and solution that  Autocad File ( Autocad 2009 version or above) is enclosed



Tutorial Electrical Planning and Designing for Contractor, College, Student
Figure KBJ 1.1 Isometric View Building

The position of AC and Exhaust Fan are shown as figure KBJ 1.2. But the director didn't know how many WATT of them (.all these pdf file in high quality are suggested to download. )

Figure KBJ 1.2 Layout

Question : make the electrical construction of layout Figure KBJ 1.2.

Answer :
Follow these Steps:
Step 1 : Calculate the Total of Electrical Load in WATT unit , then convert into VA unit
Step 2 : Find the Main MCB and Main Cable refer to the Table or formula
Step 3 : Divide into several smaller groups ( Branch MCB ), then make the Single Line Diagram
Step 4 : Find the Grounding Cable on stick rod by formula
Step 5 : Describe  all groups  into Layout

Step 1 : Calculate the Total of Electrical Load in WATT unit , then convert into VA unit
By seeing figure KBJ 1.2 ,

a. The WATT of TL Lamp 2 x 36 WATT ----->  48 x ( TL Lamp 2 x36 WATT ) = 3456 WATT
b. The WATT of Exhaust Fan -----> 8 x 124 WATT = 992 WATT ( selected Exhaust Fan by searching google and ask for approval of the director )
c. The WATT of Loud Speaker -----> 1 x 400 WATT = 400 WATT ( selected Loud Speaker by searching google and ask for approval of the director )
d. The WATT of AC 2Hp -----> 6 x ( 2x 746 WATT ) = 11.936 WATT  ( 1 Hp = 746 WATT )
e. The WATT of Socket, we have to prepare sockets in case we need sometime  -----> 10 x 100 WATT = 1000 WATT

Total of Electrical Load in WATT = 3456 + 992 + 400 + 11.936 + 1000 = 17784 WATT

Convert WATT into VA -----------> VA = P/Cos Ø, where  P = Watt and Cos Ø = power factor,  In Indonesia the cos Ø usually about 0.85 or 0.8.
In this Blog we use Cos Ø = 0.8,  So, VA = P/Cos Ø = 17784/0.8 = 22230 VA

Step 2 : Find the Main MCB and Main Cable refer to the Table KBJ 1.a


NO
POWER ( VA )
   MCB ( Ampere )
   Main Cable
Phase Type
1
450
2
3 x 2.5 mm²
2
900
4
3 x 2.5 mm²
3
1300
6
3 x 4 mm²
4
2200
10
3 x 4 mm²
5
3500
16
3 x 4 mm²
6
4400
20
3 x 4 mm²
7
5500
25
3 x 4 mm²
8
7700
35
3 x 6 mm²
9
11000
50
3 x 6 mm²





10
6600
3 x 10
4 x 4 mm²
11
10600
3 x 16
4 x 6 mm²
12
13200
3 x20
4 x 10 mm²
13
16500
3 x 25
4 x 10 mm²
14
23000
3 x 35
4 x 16 mm²
15
33000
3 x 50
4 x 16 mm²
16
41500
3 x 63
4 x 25 mm²
17
53000
3 x 82
4 x 35 mm²
18
66000
3 x 100
4 x 50 mm²
19
82500
3 x 125
4 x 50 mm²
20
105000
3 x 160
4 x 70 mm²
21
131000
3 x 200
4 x 95 mm²
22
171000
3 x 250
4 x 120 mm²
23
197000
3 x 300
4 x 150 mm²
24
329000
3 x 500
4 x 240 mm²

Table KBJ 1.a  MCB and Cable Sizes  for Each Power ( VA)

Note :
The content of the table is adapted to the size of the MCB available in Indonesia Electrical Stores, or you can adjust the size of the MCB or Cable is available in your country by formula :

I = P / ( Vln x Cos Ø ) = VA / Vln       with Vln = V line netral = 220 Volt         …… for 1Ø
I = P / (1.73 x  Vll x Cos Ø ) = VA / ( 1.73 x Vll )    with Vll = V line line = 380 Volt  ...… for 3Ø

Example: A dozen lamps and 3 Electric Fan in your home with total 800 Watt,
So,  I = P ( Vln x cos Ø ) = 800 ( 220 x 0.85 ) = 4.3 Ampere, then you want to buy MCB at electric store, the clerk of the store simply  give you MCB 6 A, since MCB 4.3 A is not available at the store.

As described aboved that Rating Power 22230 VA associated with green color on the table KBJ 1.a , the main MCB is 3 x 35 Amperes type 3Ø, and and main cable is 4 x 16 mm²


Step 3 : Divide into several smaller groups ( Branch MCB ), then make the Single Line Diagram
For whom still don't know about 1Ø and 3Ø type can see illustrate of figure KBJ 1.3 below:

Tutorial Electrical Planning and Designing for Contractor, College, Student
Figure KBJ 1.3 Illustrate of 1Ø and 3Ø types
As describe above, The Main MCB is 3 x 35 A type 3Ø but we have to divide the MCB 3Ø into 3 pieces of MCB 1Ø they are  MCB 35A 1Ø, MCB 35A 1Ø, MCB 35A 1Ø, but MCB 35A isn't abailable in Indonesia Electrical Store instead 40A, so we have to provide the main MCB 3x40A which 3Ø and 3 of MCB 40A type 1Ø.

See the single line diagram at Figure KBJ 1.4 below which contain of Figure KBJ 1.4a and Figure KBJ 1.4b.  At Figure KBJ 1.4a only a line is used for 23000 VA , but of course we can use the other 2 line  with different KWH Meter. Refer to figure KBJ 1.4 a and b, the MCB 16 A is a higher MCB for load distribution so we get the better choice of single line diagram as shown Figure KBJ xx .

Figure KBJ 1.4 Single Line Diagram



Figure KBJ xx Alternative choice single line diagram

Step 4 : Find the Grounding Cable on stick rod by formula
Grounding Cable sizing ( usually BC Type )  that connected to stick rod is found as follows:
if S ≤ 16 mm² ,  so BC grounding’s size is S mm²
If 17 mm² ≤  S ≤ 35 mm³ , so BC grounding’s size is only 16 mm²
But if S ≥ 35 mm² , BC grounding’s size is S/2
Where S = Cable Size
So, according this equation, we got BC cable grounding that connected to stick rod about BC 16 mm²

Step 5 : Describe  all groups  into Layout
If we put all groups at once that would look be over crowded so we put one by one as shown Figure KBJ 1.5a, 1.5b and 1.5c below :

Figure KBJ 1.5a Construction for Group A


Figure KBJ 1.5b Construction for Group B



Figure KBJ 1.5c Construction for Group C

 NOTE :
Try to look the single line diagram of figure KBJ 1.5a, the both cable sizes of MCB 16A and 10A is NYM 3x4 mm2, that's not mean we have to use this size into electrical load because of too expensive, we need cheaper but secure or safety. We can divide them into several smaller size of MCB like sevral MCB 6A or 2A. Again we can divide the by ignoring MCB 6A or 2A with only using Cable 2.5 mm2 as shown in Figure KBJ 1.5a, 1.5b and 1.5c. Some Lamps and Electrical Motor 1Ø (the sample of Motor 1Ø are Fan, Refrigerator, water pump at home, ironing, hand drier, etc ) are using cable NYM or NYY 2x2.5 mm2 or 3x2.5 mm2. For figure KBJ ....you can see that lamps and Exhaust Fan are similar. The Lamps and Exhaust Fan is combineed in paralel since they have  WATT number less than 1500 WATT. But you can't do the same way using 2.5mm2 size into some AC, each AC has number WATT greater rhan 1500 WATT, we have to make wiring each AC separately. The only way to make them a paralel combine is by using 3x4 mm2 cable size.
The Lamps using cable 2x2.5 mm2 but socket using cable 3x2.5 mm2, The number 3 of socket is related to grounding if you still don,t know about this grounding on socket, you can see the illustration of Figure KBJ 1.6. Cable NYM is indoor cable type and has white color of cover, we can install this cable at home with or without pipe. The NYY type is outdoor cable and has black color of cover, we can use this cable as underground cable with put into pipe. Cable NYFGBY type is specialize underground cable without using pipe. KWH meter is usually placed  outdoor 1.8 meter high from floor and must be easy to be reach by electrical technician company. Panel is usually placed  indoor 1.6 meter high from floor and mus be easy to be reach by owner's house. Socket and Switch is usually placed  indoor 1.2 meter high from floor near rooms or doors and but the switch or socket is not hidden or covered while we open the door,You can download Autocad File version here of the PDF fictures above if you need to
Tutorial Electrical Planning and Designing for Contractor, College, Student
Figure KBJ 1.6 Socket use 2 line and Lamp uses 3 line for wiring